Patna Metro Completes First Year With Expansion Plans

Brief By Newsbrief / 9:28 AM on 06 Oct 2026


Patna Metro completed its first year of operations on October 6, 2026, after the first priority corridor was inaugurated in 2025. However, only 6.2 km of the planned 32.5-km network is currently operational, covering ISBT, Zero Mile, Bhootnath and Malahi Pakri.

The Khemnichak station, being developed as Patna Metro’s first interchange, is now targeted for completion by December 2026. From there, a 3.1-km elevated stretch to Mithapur is planned to become operational by June 2027.

To support rising ridership and network expansion, PMRCL has ordered three six-coach train sets from Pune Metro on a three-year lease. They are expected to reach Patna by December.

Meanwhile, work is progressing on Corridor-2’s underground section between Moinul Haq Stadium and Patna Junction, featuring five underground stations. Civil construction will be followed by electrical and track work, with the entire section targeted for commissioning by 2028.